Electrical switchgear cabinets arranged across a large indoor space
PLANNING GUIDES

Switchgear Wind and Seismic Design.

New electrical distribution equipment built around your project. Discuss specifications, timing and delivery with a U.S. manufacturer.

01 BUILT FOR THE WORK AHEADEquipment photograph shown for illustration.
01 /
MADE IN USAAmerican components
02 /
UL 891Low-voltage switchboards
03 /
SHORT LEAD TIMESSchedule-focused planning
04 /
NATIONWIDEShipping available
01 /

Start With the Site’s Wind and Seismic Criteria

Wind and seismic design begins with the building and installation location, not a generic enclosure description. Confirm the project’s governing code and adopted standard, the site’s design wind conditions, seismic design category or other required seismic parameters, and any owner or insurer criteria. The structural engineer of record should establish the applicable inputs and clarify whether the equipment is inside, outdoors, on a roof, or in an exposed yard. These distinctions can affect the forces transmitted to the assembly and its supports. Provide the manufacturer with the project criteria early, along with the equipment lineup and installation elevation. If criteria are not finalized, identify the assumptions in writing so procurement can track them and the design team can resolve them before approval drawings are released.

02 /

Define the Complete Equipment and Support Arrangement

A switchgear assembly is only one part of the load path. The design team should identify the equipment’s mounting method, base or channel arrangement, anchorage concept, housekeeping pad or steel support, and the building structure receiving the loads. Record adjacent walls, overhead restraints, cable trenches, and any flexible connections that could affect installation or movement. Do not assume that an enclosure’s construction alone establishes seismic suitability; the assembled equipment, its attachments, and the supporting structure must be considered together. Share available foundation and structural details with the manufacturer and the project’s structural engineer. Confirm who is responsible for anchorage design, calculations, and field verification. Making these boundaries explicit helps prevent a late gap between the switchgear submittal and the installation documents.

Copper busbars inside electrical equipment, shown for illustration
THE DETAILS BEHIND THE POWERIllustrative photograph; not represented as our facility. Photo: ToT89.
03 /

Coordinate Electrical Configuration With Mechanical Demands

Wind and seismic requirements can influence the physical arrangement of the equipment, while electrical needs constrain what can change. Document voltage class, system configuration, current and interrupting requirements, bus arrangement, protective devices, metering, cable entry, and future provisions alongside the applicable environmental criteria. Also identify doors, removable panels, ventilation openings, barriers, and service clearances that must remain usable after installation. A change to compartment layout or support details may affect access, cable bend space, heat management, or coordination with connected equipment. The manufacturer should review the requested configuration against the project documents rather than treating a structural note as an isolated accessory. Resolve conflicts among electrical drawings, architectural openings, and structural requirements during design review, before the approved arrangement is committed to fabrication.

04 /

Request Submittals That Make Review and Approval Practical

A useful procurement package tells reviewers what must be demonstrated and what evidence they should expect. Specify the governing criteria, required submittal format, review milestones, and any project-required calculations, anchorage details, equipment weights, interface information, or evaluation documentation. Ask the design team to distinguish mandatory code or contract requirements from owner preferences, and to identify the professional responsible for accepting structural calculations. Where a particular test, qualification, or listing is required, state the exact requirement and confirm its applicability to the equipment type and proposed configuration; do not infer that a general product description satisfies it. Include drawing submission and resubmission time in the project schedule. Clear review criteria reduce avoidable clarification cycles and give procurement a traceable basis for comparing proposals.

05 /

Plan Schedule Around Design Decisions and Approval Hold Points

Wind and seismic inputs affect more than fabrication; unresolved criteria can delay drawings, engineering review, foundations, and release to production. At inquiry, provide the specification, one-line diagram, equipment schedule, site criteria, preliminary layout, and target dates for submittals and delivery. Ask for a project-specific schedule that identifies assumptions, customer-furnished information, approval steps, and any decisions needed before fabrication. A short stated lead time is not a substitute for confirming that the scope, documentation, and review path are workable. Track changes to the installation location or support arrangement because revised project inputs may require renewed coordination. For replacement work, document existing access, outage constraints, and connection interfaces early; the new assembly must still meet the project’s approved requirements and be installed under the site’s safety procedures.

06 /

Coordinate Shipping, Receiving, and Final Installation

Delivery planning should reflect the actual route from carrier access to the final equipment position. Check doorway and corridor dimensions, floor loading, turning space, overhead obstructions, unloading equipment, staging area, weather exposure, and whether the assembly can travel as a complete lineup or must be handled in sections. Confirm shipping configuration, lifting or handling information, receiving responsibilities, and site access dates with the manufacturer before dispatch. For outdoor or coastal locations, specify relevant exposure and protection requirements rather than assuming that wind design also addresses corrosion or water intrusion. Nationwide shipping does not establish a site’s unloading capability or delivery appointment. Align the shipment with a ready foundation, approved drawings, qualified installation personnel, and a planned outage where needed; perform installation and verification with equipment de-energized.

THE DETAILS MATTER

Project
specifications.

Bring your requirements to the conversation. Final configurations are determined by the project scope and applicable standards.

Specifications and project considerations
ParameterProject consideration
ApplicationSwitchgear Wind and Seismic Design
Voltage and configurationProject-specific; confirm in quotation
Continuous current and busProject-specific; confirm in quotation
Short-circuit ratingProject-specific; confirm in quotation
Standards and certificationAs applicable; verify for the proposed assembly
Component originAll-American options; confirm in quotation
Lead time and shippingProject-specific; nationwide shipping available
LET'S BUILD SOMETHING

Your project
starts here.

Tell us what you are planning. Share the details you have, and start a conversation about new equipment built for the job.

PREFER TO TALK?
(951) 403-5738
HOUSTON, TEXAS / NATIONWIDE
PROJECT INQUIRY

Request a quote

Fields marked with an asterisk are required.

Submitting opens your email application with your inquiry. Please send the prepared email to complete your request; no information is submitted through this website.

REQUEST A QUOTE